Timeline Report

Author: CivicbroadsidePublished: 2026-09-24Method: JSON Data and ElementTree (CLEAR-DOCS Framework)

1. Conceptualization & Seed Phase (Sep 2019 – Dec 2020)

Focus: Community engagement, conceptual visioning, and initial climate-resilience strategy.

Budget Base: ~$300,000 (Planning, public process, and conceptual study)

2. Engineering, Technical Design & Local Seed Capital (Jan 2021 – Jun 2023)

Focus: Transitioning conceptual ideas into engineered schematics and securing local commitment.

Budget Base: ~$1.2 Million (Design, site testing, and environmental permitting)